ZG Commissioning Terms and Conditions

  1. 1.All electrical installations shall be completed, installed and tested in accordance with the current edition of the IET Wiring Regulations.
  2. 2.All applicable health and safety regulations shall be complied with on site. Statutory welfare facilities shall be made available to ZGUK employees and their appointed service agents at all times.
  3. 3.Any site-specific health and safety training required before permission to commence work is granted must be communicated to ZGUK in writing when the commissioning engineer is requested. Where such training falls outside the allocated commissioning period, ZGUK reserves the right to apply additional charges.
  4. 4.Two copies of accurate, up to date “as-installed” drawings showing equipment locations shall be provided for use by ZGUK commissioning engineers.
  5. 5.A minimum of 10 working days’ notice is required to allow commissioning activities to be scheduled.
  6. 6.ZGUK must receive written instruction confirming the commissioning visit before the engineer attends site. The instruction must specify the intended visit date.
  7. 7.Commissioning assumes that the installation is complete, operational and free from faults. Where the commissioning engineer is required to undertake fault-finding or assist with rectification due to faulty workmanship or incorrect installation, or where a return visit is required because the installation is incomplete, additional charges will apply.
  8. 8.Throughout the commissioning period, a site operative who is fully familiar with the installation shall be available at all times, at no additional cost to ZGUK. The operative shall work alongside the ZGUK commissioning engineer and provide information and assistance relating to lighting circuits, repairs, equipment locations, isolations, access requirements and other relevant site matters. The operative must be suitably competent and authorised to operate lighting circuits, carry out isolations and facilitate access to equipment where required. Responsibility for electrical safety, isolation procedures and the safe operation of the installation shall remain with the site contractor or installer.
  9. 9.All lighting circuits must remain undisturbed throughout commissioning. All luminaires must be installed, and the batteries of all emergency luminaires must be connected.
  10. 10.Any access equipment required to safely carry out commissioning activities shall be provided by the site contractor or installer. The provision of access equipment is excluded from commissioning service charges.
  11. 11.Commissioning activities shall be carried out between 08:00 and 16:00, Monday to Friday, excluding public holidays unless otherwise agreed.
  12. 12.Commissioning services do not include electrical installation work.
  13. 13.Adequate lighting and power supplies shall be provided on site to facilitate commissioning activities.
  14. 14.It is recommended that the person or persons ultimately responsible for operating and maintaining the system, such as the Facilities Manager or Maintenance Electrician, are available at the conclusion of commissioning for training. Training provided outside the allocated commissioning period will be subject to additional change.